Drivers of Delays in Procurement of Infrastructure Projects
The objective of this study was to analyze the reasons for delays in procurement and contract execution of infrastructure projects. It analyzes available data from three different sources: Tender data for 656 works contracts extracted from the World Bank Systematic Tracking of Exchanges in Procurement (STEP), covering the period 2013-2022. This sample was used to analyze the incidence and extent of delays in the procurement of World Bank infrastructure projects; A sample of 312 works contracts for infrastructure projects financed by the World Bank and the Islamic Development Bank (IsDB), covering the period 2007-2019. This sample was used to analyze the reasons for delays in the procurement and delivery of World Bank and IsDB infrastructure projects at the contract level; CoST assurance reports from 2016 to 2020 covering 480 infrastructure projects across 12 member countries of CoST. This sample was used to analyze the reasons of delays for the reviewed infrastructure projects.
Main Author: | |
---|---|
Format: | Report biblioteca |
Language: | English en_US |
Published: |
Washington, DC: World Bank
2024-07-31
|
Subjects: | PROCUREMENT LAW, PUBLIC PROCUREMENT AND COMPETITION, PROCUREMENT PLANNING, INDUSTRY, INNOVATION AND INFRASTRUCTURE, SDG 9, PARTNERSHIP FOR THE GOALS, SDG 17, |
Online Access: | http://documents.worldbank.org/curated/en/099062824153516589/P173110138cdf70ef18cd21fb78946336ef https://hdl.handle.net/10986/41978 |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | The objective of this study was to
analyze the reasons for delays in procurement and
contract execution of infrastructure projects. It analyzes
available data from three different sources: Tender data for
656 works contracts extracted from the World Bank Systematic
Tracking of Exchanges in Procurement (STEP), covering the
period 2013-2022. This sample was used to analyze the
incidence and extent of delays in the procurement of World
Bank infrastructure projects; A sample of 312 works contracts
for infrastructure projects financed by the World Bank and
the Islamic Development Bank (IsDB), covering the period
2007-2019. This sample was used to analyze the reasons for
delays in the procurement and delivery of World Bank and
IsDB infrastructure projects at the contract level; CoST
assurance reports from 2016 to 2020 covering 480
infrastructure projects across 12 member countries of CoST.
This sample was used to analyze the reasons of delays for
the reviewed infrastructure projects. |
---|